Week 79: Front Doors Put In

 

 

We are 2 1/2 weeks away from the opening night, Friday September 12 at 7:30. The installation of the marble behind and on the pulpit is planned for Thursday. A shipment of furniture should also be coming on Thursday. This Saturday the gardens will be planted and the sod will be installed over the next two weeks. Next week the organ will be tuned and since total silence is needed, the paving that was planned for next week has been pushed to the week of the 7th. Crews of cleaners from our church have been busy and their work is very noticeable.

 

DSC_2029 DSC_2031 DSC_2034 DSC_2035 DSC_2036 DSC_2037 DSC_2039 DSC_2042 DSC_2044 DSC_2045 DSC_2050 DSC_2051 DSC_2054 DSC_2056 DSC_2062 DSC_2063

Week 74: The pews and pulpit arrive

I took these photos on Wednesday and Thursday. I will not be around next week when the pews are assembled, so you will have to visit the church to see the progress or you can wait for pictures the week after next.

DSC_0046DSC_0037DSC_0035DSC_0063 DSC_0062 DSC_0058 DSC_0056 DSC_0055 DSC_0065DSC_0049  DSC_0042  DSC_0036  DSC_0034 DSC_0033 DSC_0032

Week 72: Organ Installation

Week 71: Sanctuary Interior Progresses

A lot has happened over the last two weeks. If all things go as planned, the organ installation should begin in a week. The dedication service has been scheduled for September 12, D.V.

Week 59: Sanctuary Floor Poured (1)

Week 58: Mud, Tile & Stained Glass

Now that its spring, the mud is thick and deep

Now that its spring the mud is thick and deep

The window on the left has had the broken panes replaced is completely installed

The window on the left has had the broken panes replaced is completely installed

The glass for the rose window has been installed

The glass for the front windows is being replaced where needed

This lift is stuck in the mud as well

Both lifts were stuck in the mud

Trying to get it out

Trying to get it out

The lampposts have now been installed in the parking lot

The lampposts have now been installed in the parking lot

The babysit exterior wall is now finished

The babysit exterior wall is now finished

The framing of the ceiling in the sanctuary is done

The framing of the ceiling in the sanctuary is done

A glimpse through the glass

A glimpse through the glass

Working on putting down the rebar for the concrete pours coming next week Monday, Tuesday and Wednesday

Working on putting down the rebar for the concrete pours coming next week Monday, Tuesday and Wednesday

The tile has been laid in the kitchen

The tile has been laid in the kitchen

A tile accent on the wall of the nursery

A tile accent on the wall of the nursery

One was also installed in the toddler room

One was also installed in the toddler room

A tree being taken down behind the church

A tree being taken down behind the church

Working on the drywall

Working on the drywall

Week 53: One Year Down

The old church building taken before it all began.

The old church building, the photo taken before it all began.

The building project has been going on for more than year now. I’ve published 83 posts comprising of 765  photos. The day with the most blog traffic was March 13, 2013 when I posted some pictures of the demolition. If you scroll to the very bottom of the page, I’ve put up a blog archives and a categories section where you can browse older posts.